A project manager believes that modifying the scope of the project may provide added value

for the customer. The project manager should:

A.Change the scope baseline

B.Prepare a variance report

C.Call a meeting of the configuration control board

D.Change the project's objectives

E.Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“A project manager believes tha…”相关的问题
第1题
The scope baseline/project charter is prepared by the:AProject managerBProject manager and

The scope baseline/project charter is prepared by the:

AProject manager

BProject manager and project office

CProject manager, project office and functional team

DProject manager, project office, functional team and project sponsor

EProject manager, project sponsor and customer/user

点击查看答案
第2题
121The quality objectives are approved in the conceptual stage of the project by the: A.Pr

121 The quality objectives are approved in the conceptual stage of the project by the:

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner

点击查看答案
第3题
The main player in project communication is theAsponsorBproject managerCfunctional manager

The main player in project communication is the

A sponsor

B project manager

C functional manager

D functional team

E All of the above.

点击查看答案
第4题
112Of the following, who has the ultimate responsibility for meeting project quality objec

112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner

点击查看答案
第5题
A project manager can exchange information with the project team using which media?Atactil

A project manager can exchange information with the project team using which media?

A tactile

B audio

C olfactory

D visual

E All of the above.

点击查看答案
第6题
92The main player in project communication is the A.sponsor B.project manager C.functional

92 The main player in project communication is the

A. sponsor

B. project manager

C. functional manager

D. functional team

E. All of the above

点击查看答案
第7题
A project manager trying to communicate accurately to the team should use:Athe language of

A project manager trying to communicate accurately to the team should use:

A the language of the team members

B the language of the project manager

C non-verbal methods

D written memos

E All of the above.

点击查看答案
第8题
Project leadership requires that the project manager pay attention simultaneously to the:A

Project leadership requires that the project manager pay attention simultaneously to the:

A . Tasks to be performed and needs of the team

B . Quantity and quality of the work to be performed

C . Efficiency and effectiveness of the team

D . Time, cost and performance deliverables

E . All of the above

点击查看答案
第9题
Of the following, who has the ultimate responsibility for meeting project quality objectiv
es?

A . Project Engineer

B . Project Manager

C . Functional Manager

D . Quality Assurance Manager

E . Project Owner

点击查看答案
第10题
93When a project manager is running over the budgeted costs, the project manager can typic

93 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.

A. Reduce features and/or functionality

B. Increase risk.

C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)

D. All of the above.

E. A and B only

点击查看答案
第11题
The project charter is developed by:A.senior managementB.the customerC.the project manager

The project charter is developed by:

A.senior management

B.the customer

C.the project manager

D.both A and C

E.None of the above.

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改