![](https://static.youtibao.com/asksite/comm/h5/images/m_q_title.png)
The project charter is developed by:A.senior managementB.the customerC.the project manager
The project charter is developed by:
A.senior management
B.the customer
C.the project manager
D.both A and C
E.None of the above.
![](https://static.youtibao.com/asksite/comm/h5/images/solist_ts.png)
The project charter is developed by:
A.senior management
B.the customer
C.the project manager
D.both A and C
E.None of the above.
The scope baseline/project charter is prepared by the:
AProject manager
BProject manager and project office
CProject manager, project office and functional team
DProject manager, project office, functional team and project sponsor
EProject manager, project sponsor and customer/user
A.Conceptual, charter/baseline.
B.Conceptual, master schedule.
C.Development, charter/baseline.
D.Development, master schedule.
E.Development, masterplan.
AThe project manager
BThe project office
CThe project team
DThe project sponsor
EAnyone associated with the project
35 The project charter:
A. Expresses upper management commitment to the project.
B. Provides that authority by which the project will be run.
C. Establishes that organizational structure with the project.
D. Specifies overall objectives and timeframe. of the project.
E. All of the above
111 It is useful to conduct project risk assessment according to the project's
A. charter
B. statement of work
C. Work Breakdown structure
D. network
E. budget
The project charter:
A.Expresses upper management commitment to the project.
B.Provides that authority by which the project will be run.
C.Establishes that organizational structure with the project.
D.Specifies overall objectives and timeframe. of the project.
E.All of the above.
It is useful to conduct project risk assessment according to the project's
A charter
B statement of work
C Work Breakdown structure
D network
E budget
● The initial document that formally recognizes the existence of a project is the _____ .
A Scope baseline
B Management plan
C Project charter
D Configuration control report
E None of the above
159 The project scope/charter baseline includes:
A. Summary of background conditions defining the project.
B. Organization, authority and responsibility relationships.
C. Functions to be performed.
D. Resource requirement schedule including time estimates.
E. All of the above
The project scope/charter baseline includes:
A.Summary of background conditions defining the project.
B.Organization, authority and responsibility relationships.
C.Functions to be performed.
D.Resource requirement schedule including time estimates.
E.All of the above.