As a control tool, the bar chart (Gantt) methods is most beneficial for:A.rearranging conf

As a control tool, the bar chart (Gantt) methods is most beneficial for:

A.rearranging conflicting tasks

B.depicting actual versus planned tasks

C.showing the outer dependencies of tasks

D.A and C.

E.A and D

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“As a control tool, the bar cha…”相关的问题
第1题
The work breakdown structure (WBS) is an excellent tool for objective control and evaluati

The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

A.Time, schedule and cost.

B.Management coordination and organization structuring.

C.Work methods and accountability.

D.Quality of work.

E.Risk and impact decision-making.

点击查看答案
第2题
146The work breakdown structure (WBS) is an excellent tool for objective control and evalu

146 The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

A. Time, schedule and cost.

B. Management coordination and organization structuring.

C. Work methods and accountability.

D. Quality of work.

E. Risk and impact decision-making

点击查看答案
第3题
32Financial compensation is the primary motivational tool for which of the following manag

32 Financial compensation is the primary motivational tool for which of the following management theories of programs.

A. Zero-defects program.

B. theory X management.

C. theory Y management.

D. Quality control circles.

E. A and C

点击查看答案
第4题
Which quality management tool would be used to determine potential causes of a production
problem?

A . control chart.

B . Ishikawa diagram.

C . scatter diagram.

D . histogram.

E . run chart.

点击查看答案
第5题
169Which quality management tool would be used to determine potential causes of a producti

169 Which quality management tool would be used to determine potential causes of a production problem?

A. control chart.

B. Ishikawa diagram.

C. scatter diagram.

D. histogram.

E. run chart

点击查看答案
第6题
To determine what causes the majority of quality problems in a process, a very useful tool
is the:

A . cause and effect diagrams.

B . flow chart.

C . control chart.

D . pareto chart.

E . trend chart.

点击查看答案
第7题
In performing an impact analysis, the most effective tool to ensure all risks are identifi
ed on large projects is the:

A Work breakdown structure

B milestone review and schedule technique

C cost/schedule control system

D planning programming budget system

E program and evaluation review technique

点击查看答案
第8题
An acceptance control chart has limits that are based on the spec. limits for the product
rather than limits which differentiate between random and assignable causes. Under which of the following circumstances should a QC manager consider this type chart

A . When the engineering tolerance on a dimension greatly exceeds the natural dispersion of the manufacturing process

B . When the number of samples outside the current control chart limits become too costly and cumbersome to investigate.

C . When a process is subject to constant but stable tool wear.

D . A and B.

E . A and C

点击查看答案
第9题
When he realized that he couldn't control the car, he was scared and()

A.oppressed

B.depressed

C.suppressed

点击查看答案
第10题
It is five years since I was ______ with them, so I don't know how they are getting along.

A.out of control

B.out of the question

C.out of touch

D.out of sight

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改