Using the WBS shown in the Special window, a typical work package would be:ASoftware devel
Using the WBS shown in the Special window, a typical work package would be:
ASoftware development
BSystems design
CCoding
DA, B, and C
ENone of the above.
Using the WBS shown in the Special window, a typical work package would be:
ASoftware development
BSystems design
CCoding
DA, B, and C
ENone of the above.
Which of the following can be tracked using the WBS?
A.time
B.cost
C.performance
D.scope
E.None of the above.
Using the WBS in the Special window, an instance of a work package is:
A.Build house
B.Excavate
C.Prepare Foundation
D.B and C
E.None of the above
A . Over, 16.66
B . Under, 16.66
C . Over, 10.0
D . Under, 10.0
E . None of the above.
A . Element P
B . Element Q
C . Element R
D . Element S
E None of the above.
Using the possible loss outcomes shown in the Special window, find the expected (loss)
A ¥0
B ¥-1,300
C ¥-2,000
D ¥-3,000
E None of the above
Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:
A . 1.1
B . 0.9
C . 0.956
D . 1.15
E . 0.869
A . Element P
B . Element Q
C . Element R
D . Element S
E . None of the above.
A ¥-1,000
B ¥1,000
C ¥2,000
D ¥1,200
E None of the above
A . P
B . Q
C . R
D . S
E . T
(61)
A.that
B.what
C.which
D.it