A line manager provides you with three estimates for his activity in your PERT network. Hi
A . 4 weeks
B . 5 weeks
C . 6 weeks
D . 7 weeks
E . None of the above.
A . 4 weeks
B . 5 weeks
C . 6 weeks
D . 7 weeks
E . None of the above.
4 During project execution, a line manager informs you that he will not have sufficient resources available next month to support your and two other projects. The best way to handle this problem would be to:
A. Ask the line manager to make the decision.
B. Ask the line manager to work with senior management to prioritize the work.
C. Ask your sponsor to meet with the line manager.
D. Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.
E. Prepare a purchase order to outsource the work
17 A line manager who is asked to wear two hats and function as a project manager at the same time is likely to exercise:
A. Authority
B. Power
C. Influence
D. All of the above]
E. A and B only
A.Ask the line manager to make the decision.
B.Ask the line manager to work with senior management to prioritize the work.
C.Ask your sponsor to meet with the line manager.
D.Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.
E.Prepare a purchase order to outsource the work.
164 A line manager possesses information which the project team needs, but withholds the information. The results in a(n):
A. Blindspot
B. Facade
C. region of influence
D. Communication power base
E. None of the above
78 The major difference between project and line management is that the project manager may not have any control over which basic management function?
A. Decision-making
B. Staffing
C. Rewarding
D. Tracking/monitoring
E. Reviewing
A Authority
B Power
C Influence
D All of the above]
E A and B only
124 A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:
A. 4 weeks
B. 5 weeks
C. 6 weeks
D. 7 weeks
E. None of the above
A.Line Manager
B.2T & 2C
C.IT
D.SP
E.HR
A Blindspot
B Facade
C region of influence
D Communication power base
E None of the above