首页 > 职业资格考试> 项目管理师
题目内容 (请给出正确答案)
[主观题]

A line manager provides you with three estimates for his activity in your PERT network. Hi

s estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:

A . 4 weeks

B . 5 weeks

C . 6 weeks

D . 7 weeks

E . None of the above.

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“A line manager provides you wi…”相关的问题
第1题
4During project execution, a line manager informs you that he will not have sufficient res

4 During project execution, a line manager informs you that he will not have sufficient resources available next month to support your and two other projects. The best way to handle this problem would be to:

A. Ask the line manager to make the decision.

B. Ask the line manager to work with senior management to prioritize the work.

C. Ask your sponsor to meet with the line manager.

D. Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.

E. Prepare a purchase order to outsource the work

点击查看答案
第2题
17A line manager who is asked to wear two hats and function as a project manager at the sa

17 A line manager who is asked to wear two hats and function as a project manager at the same time is likely to exercise:

A. Authority

B. Power

C. Influence

D. All of the above]

E. A and B only

点击查看答案
第3题
During project execution, a line manager informs you that he will not have sufficient reso
urces available next month to support your and two other projects. The best way to handle this problem would be to:

A.Ask the line manager to make the decision.

B.Ask the line manager to work with senior management to prioritize the work.

C.Ask your sponsor to meet with the line manager.

D.Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.

E.Prepare a purchase order to outsource the work.

点击查看答案
第4题
新增人才中“联系人”指的客户公司的联系人(譬如HR/Line Manager等)()
点击查看答案
第5题
164A line manager possesses information which the project team needs, but withholds the in

164 A line manager possesses information which the project team needs, but withholds the information. The results in a(n):

A. Blindspot

B. Facade

C. region of influence

D. Communication power base

E. None of the above

点击查看答案
第6题
78The major difference between project and line management is that the project manager may

78 The major difference between project and line management is that the project manager may not have any control over which basic management function?

A. Decision-making

B. Staffing

C. Rewarding

D. Tracking/monitoring

E. Reviewing

点击查看答案
第7题
A line manager who is asked to wear two hats and function as a project manager at the same
time is likely to exercise:

A Authority

B Power

C Influence

D All of the above]

E A and B only

点击查看答案
第8题
124A line manager provides you with three estimates for his activity in your PERT network.

124 A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:

A. 4 weeks

B. 5 weeks

C. 6 weeks

D. 7 weeks

E. None of the above

点击查看答案
第9题
入职后需要申请1台办公电脑,金额6000元(预算内固定资产),在采购(OneSRM)系统中分别需要哪些部门的审批()

A.Line Manager

B.2T & 2C

C.IT

D.SP

E.HR

点击查看答案
第10题
The electronic company you work for has decided to recruit some employees, and the Personn
el Department Manager has asked all the department managers to hand in their talent demand. Write an email to the Personnel Department Manager: saying how many staff your department need and why describing what kind of person you need stating when the staff should come to work. Write 40-50 words. To: Personnel Department Manager From: The Line Manager Date: Subject: Talent Demand

点击查看答案
第11题
A line manager possesses information which the project team needs, but withholds the infor
mation. The results in a(n):

A Blindspot

B Facade

C region of influence

D Communication power base

E None of the above

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改