The manager would rather his daughter______in the same office.A.had not workedB.not to wor
The manager would rather his daughter______in the same office.
A.had not worked
B.not to work
C.does not work
D.did not work
The manager would rather his daughter______in the same office.
A.had not worked
B.not to work
C.does not work
D.did not work
A.some time
B.sometime
C.sometimes
D.some times
13 The major reason why a project manager would use written instead of oral communication is: A. documentation
B. feedback
C. cost
D. barrier elimination
E. All of the above
A.bridge
B.brigade
C.break
D.brick
A documentation
B feedback
C cost
D barrier elimination
E All of the above.
How could a manager deal with conflict?
A.If his superior is involved, he should be the third party of it.
B.He should punish the person who is responsible for the conflict.
C.He might consider whether to interfere with the matter or not.
D.He would not consider his relationship with the two adversaries.
124 A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:
A. 4 weeks
B. 5 weeks
C. 6 weeks
D. 7 weeks
E. None of the above
A.Ask the line manager to make the decision.
B.Ask the line manager to work with senior management to prioritize the work.
C.Ask your sponsor to meet with the line manager.
D.Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.
E.Prepare a purchase order to outsource the work.
A . 4 weeks
B . 5 weeks
C . 6 weeks
D . 7 weeks
E . None of the above.
4 During project execution, a line manager informs you that he will not have sufficient resources available next month to support your and two other projects. The best way to handle this problem would be to:
A. Ask the line manager to make the decision.
B. Ask the line manager to work with senior management to prioritize the work.
C. Ask your sponsor to meet with the line manager.
D. Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.
E. Prepare a purchase order to outsource the work