A project manager who, in a deference of opinion with the project controls engineer on how

costs are to be reported, dictates the format of the cost report may be said to have a conflict management style.

A Withdrawing

B Forcing

C Confrontational

D Authoritarian

E Combative

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“A project manager who, in a de…”相关的问题
第1题
The scope baseline/project charter is prepared by the:AProject managerBProject manager and

The scope baseline/project charter is prepared by the:

AProject manager

BProject manager and project office

CProject manager, project office and functional team

DProject manager, project office, functional team and project sponsor

EProject manager, project sponsor and customer/user

点击查看答案
第2题
121The quality objectives are approved in the conceptual stage of the project by the: A.Pr

121 The quality objectives are approved in the conceptual stage of the project by the:

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner

点击查看答案
第3题
92The main player in project communication is the A.sponsor B.project manager C.functional

92 The main player in project communication is the

A. sponsor

B. project manager

C. functional manager

D. functional team

E. All of the above

点击查看答案
第4题
93When a project manager is running over the budgeted costs, the project manager can typic

93 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.

A. Reduce features and/or functionality

B. Increase risk.

C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)

D. All of the above.

E. A and B only

点击查看答案
第5题
The main player in project communication is theAsponsorBproject managerCfunctional manager

The main player in project communication is the

A sponsor

B project manager

C functional manager

D functional team

E All of the above.

点击查看答案
第6题
112Of the following, who has the ultimate responsibility for meeting project quality objec

112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner

点击查看答案
第7题
Ensuring that all work is both authorized and funded by contractual documentation is the r
esponsibility of:

AThe project manager

BThe functional manager

CThe project sponsor

DThe client

EAll of the above

点击查看答案
第8题
A project manager can exchange information with the project team using which media?Atactil

A project manager can exchange information with the project team using which media?

A tactile

B audio

C olfactory

D visual

E All of the above.

点击查看答案
第9题
The way a project manager sends and receives information depends upon:AHow others relate t

The way a project manager sends and receives information depends upon:

A How others relate to the project manager

B The project manager's level in the organizational hierarchy

C the size and nature of the project

D the project manager's salary and age

E the number of projects going on at one time in the company

点击查看答案
第10题
A project manager trying to communicate accurately to the team should use:Athe language of

A project manager trying to communicate accurately to the team should use:

A the language of the team members

B the language of the project manager

C non-verbal methods

D written memos

E All of the above.

点击查看答案
第11题
84Risk management allows the project manager and the project team to: A.eliminate most ris

84 Risk management allows the project manager and the project team to:

A. eliminate most risks during the planning phase of the project

B. identify project risks

C. identify impacts of various risks

D. plan suitable responses

E. B, C and D only

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改