题目内容 (请给出正确答案)
[主观题]

The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost co

The Work Breakdown Structure (WBS) is the basis for communicating:

A.Project scope, cost control, schedule, quality

B.Project objectives, dependencies, plan, cost control

C.Project scope, schedule, staffing, cost control

D.Project scope, quality, schedule, dependencies

E.Project budget, schedule, risk factors, work assignments.

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“The Work Breakdown Structure (…”相关的问题
第1题
131The work breakdown structure, the work packages, and the company's accounting system ar

131 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:

A. Code of accounts.

B. Overhead rates.

C. Budgeting system.

D. Capital budgeting process.

E. All of the above

点击查看答案
第2题
111It is useful to conduct project risk assessment according to the project's A.charter B.

111 It is useful to conduct project risk assessment according to the project's

A. charter

B. statement of work

C. Work Breakdown structure

D. network

E. budget

点击查看答案
第3题
It is useful to conduct project risk assessment according to the project'sAcharterBstateme

It is useful to conduct project risk assessment according to the project's

A charter

B statement of work

C Work Breakdown structure

D network

E budget

点击查看答案
第4题
The work breakdown structure, the work packages, and the company's accounting system are t
ied together through the:

A . Code of accounts.

B . Overhead rates.

C . Budgeting system.

D . Capital budgeting process.

E . All of the above.

点击查看答案
第5题
68The starting point in the development of a top-down PERT/CPM chart is the _____ . A.Proj

68 The starting point in the development of a top-down PERT/CPM chart is the _____ .

A. Project specification tree.

B. Customer's deliverable list.

C. Customer's milestone dates.

D. Work breakdown structure.

E. Listing of customer team meeting dates

点击查看答案
第6题
45A clear definition of the user's needs serves as the direct basis for the: A.Work breakd

45 A clear definition of the user's needs serves as the direct basis for the:

A. Work breakdown structure.

B. Functional requirements.

C. Project cost estimate.

D. Selection of personnel.

E. Termination decision.

点击查看答案
第7题
A work breakdown structure is most useful for:A.identifying individual tasks for a project

A work breakdown structure is most useful for:

A.identifying individual tasks for a project

B.scheduling the start of tasks

C.developing a cost estimate

D.determining potential delays

E.A and C

点击查看答案
第8题
The work breakdown structure (WBS) is an excellent tool for objective control and evaluati

The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

A.Time, schedule and cost.

B.Management coordination and organization structuring.

C.Work methods and accountability.

D.Quality of work.

E.Risk and impact decision-making.

点击查看答案
第9题
The work breakdown structure (WBS) is first developed in which scope management process?A.

The work breakdown structure (WBS) is first developed in which scope management process?

A . Initiation

B . Scope planning

C . Scope change control

D . Scope Definition

E . Scope verification

点击查看答案
第10题
106The "control points" in the work breakdown structure used for isolated assignments to w

106 The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:

A. Work packages.

B. Subtasks.

C. Tasks.

D. Code of accounts.

E. Integration points

点击查看答案