首页 > 职业资格考试> 项目管理师
题目内容 (请给出正确答案)
[主观题]

15Total project risk can be defined as: A.the sum of the probabilities of project risks ev

15 Total project risk can be defined as:

A. the sum of the probabilities of project risks events times the sum of consequences of those risks

B. the sum of the products of each project risk event times its consequences

C. the sum of the consequences of all project risk events

D. the sum of the probabilities of all project risk events

E. 1 - the sum of the probabilities of all project risk events

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“15Total project risk can be de…”相关的问题
第1题
Total project risk can be defined as:Athe sum of the probabilities of project risks events

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.

点击查看答案
第2题
125In Project Risk Management, Risk Response may include actions to: A.reduce the probabil

125 In Project Risk Management, Risk Response may include actions to:

A. reduce the probability of risk events

B. change the scope, budget, schedule or quality specifications of the project

C. reduce the consequences or severity of impacts of a potential risk event

D. A and C

E. All of the above

点击查看答案
第3题
It is useful to conduct project risk assessment according to the project'sAcharterBstateme

It is useful to conduct project risk assessment according to the project's

A charter

B statement of work

C Work Breakdown structure

D network

E budget

点击查看答案
第4题
In Project Risk Management, Risk Response may include actions to:Areduce the probability o

In Project Risk Management, Risk Response may include actions to:

A reduce the probability of risk events

B change the scope, budget, schedule or quality specifications of the project

C reduce the consequences or severity of impacts of a potential risk event

D A and C

E All of the above.

点击查看答案
第5题
85The purpose of project Risk Management is to: A.Identify those factors that will adverse

85 The purpose of project Risk Management is to:

A. Identify those factors that will adversely impact project objectives.

B. Assess the impact of adverse project factors.

C. Assess the probability of adverse project factors.

D. A and C

E. All of the above

点击查看答案
第6题
111It is useful to conduct project risk assessment according to the project's A.charter B.

111 It is useful to conduct project risk assessment according to the project's

A. charter

B. statement of work

C. Work Breakdown structure

D. network

E. budget

点击查看答案
第7题
23Which of the following actions is an example of risk response: A.adjust project paramete

23 Which of the following actions is an example of risk response:

A. adjust project parameters (scope, time, quality ...)

B. reduce the probability of potential project risk events C. reduce the consequences of potential project risk events

D. wait until a problem actually happens, then deal with it in the most effective and efficient manner.

E. A, B and C only

点击查看答案
第8题
Risk management allows the project manager and the project team to:Aeliminate most risks d

Risk management allows the project manager and the project team to:

A eliminate most risks during the planning phase of the project

B identify project risks

C identify impacts of various risks

D plan suitable responses

E B, C and D only

点击查看答案
第9题
Project tradeoffs are usually made by comparing _____ and constraints.ATime, cost, and qua

Project tradeoffs are usually made by comparing _____ and constraints.

ATime, cost, and quality

BTime, risk, and quality

CRisk, quality, and manpower availability

DCost, quality, and technical performance

ECost, quality, and risk

点击查看答案
第10题
Amount at Stake is the _____ .Afunction of planned time/real time project costs.Brisk iden

Amount at Stake is the _____ .

A function of planned time/real time project costs.

B risk identified in successful project completions.

C (Standard Project Deviation + Expected Costs)/6

D cost of investment loss + least cost to restore status quo.

E inherent risk at conception altered by standard project deviations.

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改