题目内容 (请给出正确答案)
[主观题]

Contingency planning should include all but which of the following?AThe development of a c

Contingency planning should include all but which of the following?

A The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.

B the development of schedule alternatives and work-around

C the management of a contingency budget

D an assessment of project shut-down liabilities.

E A and C

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“Contingency planning should in…”相关的问题
第1题
What contingency factors might the planning Habitat executives have to do for the wise use of his gift? How might those contingency affect the panning?"
What contingency factors might the planning Habitat executives have to do for the wise use of his gift? How might those contingency affect the panning?"

点击查看答案
第2题
Response Planning is the responsibility of the functional areas and considersAmitigation.B

Response Planning is the responsibility of the functional areas and considers

A mitigation.

B deflection.

C contingency planning.

D unforeseen occurrences.

E All of the above.

点击查看答案
第3题
Planning activities such that predetermined resource availability pools are not exceeded i
s called:

A.Resource leveling.

B.Manpower leveling.

C.Resource limited planning.

D.Manpower planning.

E.Manpower contingency planning.

点击查看答案
第4题
34Planning activities such that predetermined resource availability pools are not exceeded

34 Planning activities such that predetermined resource availability pools are not exceeded is called: A. Resource leveling.

B. Manpower leveling.

C. Resource limited planning.

D. Manpower planning.

E. Manpower contingency planning

点击查看答案
第5题
Discuss the contingency factors than fret planning.

点击查看答案
第6题
According to the text, which of the following is NOT mentioned as a contingency facto

A.The location of the organization

B.The size of the organization

C.One’s position and level in the organizational hierarchy

D.Level in hierarchy

E.Importance of an activity

点击查看答案
第7题
Risks that cannot be identified or evaluated _____ .Ashould be deflected to the contractin

Risks that cannot be identified or evaluated _____ .

A should be deflected to the contracting officer.

B should be handled via contingency allowances.

C should be ignored, since they cannot be identified.

D should be ignored, since they are not covered in the Risk Assessment.

E C and D

点击查看答案
第8题
Which of the following is referred to as sunk cost:A.management reserveB.contingency fundC

Which of the following is referred to as sunk cost:

A . management reserve

B . contingency fund

C . cost budgeted for construction under water

D . expended funds over which there is no further control

E . forecasted budget over-runs

点击查看答案
第9题
Managerial Reserves are:A.allowances to account for price changes that can occur over the

Managerial Reserves are:

A.allowances to account for price changes that can occur over the life of a project.

B.incentive fees paid to managers for good performance.

C.funds used to offset poor cost or schedule estimates.

D.accounts to allocate and maintain funds for contingency programs

E.All of the above.

点击查看答案
第10题
Once the logic of a network is laid out, the project manager will conduct a forward pass a
nd backward pass through the network. This will provide information on the _____ and identification of the _____ .

A.Slack for each activity, critical path.

B.Slack for each activity, high risk activities.

C.Manpower shortages, high risk activities.

D.High risk activities, non-critical paths.

E.Manpower availability, contingency plans.

点击查看答案