A non-critical path activity is completed in half the time. Then,A.The critical path is al

A non-critical path activity is completed in half the time. Then,

A.The critical path is also reduced.

B.The slack in the path containing this activity will increase.

C.The total cost for this activity has decreased.

D.Manpower from this activity can be assigned to other activities.

E.All of the above.

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“A non-critical path activity i…”相关的问题
第1题
88A non-critical path activity is completed in half the time. Then, A.The critical path is

88 A non-critical path activity is completed in half the time. Then,

A. The critical path is also reduced.

B. The slack in the path containing this activity will increase.

C. The total cost for this activity has decreased.

D. Manpower from this activity can be assigned to other activities.

E. All of the above

点击查看答案
第2题
82Once the logic of a network is laid out, the project manager will conduct a forward pass

82 Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ . A. Slack for each activity, critical path.

B. Slack for each activity, high risk activities.

C. Manpower shortages, high risk activities.

D. High risk activities, non-critical paths.

E. Manpower availability, contingency plans

点击查看答案
第3题
Once the logic of a network is laid out, the project manager will conduct a forward pass a
nd backward pass through the network. This will provide information on the _____ and identification of the _____ .

A.Slack for each activity, critical path.

B.Slack for each activity, high risk activities.

C.Manpower shortages, high risk activities.

D.High risk activities, non-critical paths.

E.Manpower availability, contingency plans.

点击查看答案
第4题
哪个命令是查看PATH变量的值?()

A.cd$PATH

B.ls$PATH

C.echo$PATH

D.cat$PATH

点击查看答案
第5题
Activities with zero time duration are referred to as:A.Critical path activites.B.Noncriti

Activities with zero time duration are referred to as:

A.Critical path activites.

B.Noncritical path activities.

C.Slack time activities.

D.Dummies

E.None of above.

点击查看答案
第6题
The critical path in a schedule network is the path that:A.Takes the longest time to compl

The critical path in a schedule network is the path that:

A.Takes the longest time to complete

B.Must be done before any other tasks

C.Allows some flexibility in scheduling a start time.

D.Is not affected by schedule slippage

E.All of the above.

点击查看答案
第7题
The critical path in a network is the path that:A.Has the greatest degree of risk.B.Will e

The critical path in a network is the path that:

A.Has the greatest degree of risk.

B.Will elongate the project if the activities on this path take longer than anticipated.

C.Must be completed before all other paths.

D.All of the above.

E.A and B only.

点击查看答案
第8题
Which command is used to initiate the Call Path Tracing function?()

A.RACP

B.RACTI

C.RAPTI

点击查看答案
第9题
The schedule risk is the _____ .Athe accumulated "expected' durations which maintain proje

The schedule risk is the _____ .

A the accumulated "expected' durations which maintain project completion.

B Critical Path adjusted by "high-risk" activity float.

C highest risk path that maintains quality.

D Critical Path when calculated with "most likely" duration.

E highest risk path that contributes the most risk toward the project completion.

点击查看答案
第10题
Using the figure in the Special window, The Critical path is _____ weeks.A.21B.22C.23D.24E

Using the figure in the Special window, The Critical path is _____ weeks.

A . 21

B . 22

C . 23

D . 24

E . 25

点击查看答案