12Overlapping activities on a project, such as design and construction, is referred to as:
12 Overlapping activities on a project, such as design and construction, is referred to as:
A. Fast tracking
B. Risk conversion.
C. Parallel management.
D. Process improvement.
E. Synchronous manufacturing