首页 > 职业资格考试> 项目管理师
题目内容 (请给出正确答案)
[主观题]

During a project review meeting, you discover that your $250,000 project has a negative sc

hedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:

A . The project will be completed late.

B . The critical path has been lengthened.

C . the costs are being overrun.

D . Overtime will be required to maintain the original critical path.

E . None of the above.

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“During a project review meetin…”相关的问题
第1题
Project alternatives are examined during the _____ phase of the projectA.conceptualB.finis

Project alternatives are examined during the _____ phase of the project

A . conceptual

B . finish

C . development

D . implementation

E . A and C

点击查看答案
第2题
During which phase of the project life cycle is the amount at stake lowest?AconceptBdevelo

During which phase of the project life cycle is the amount at stake lowest?

A concept

B development

C execution

D conclusion

E C and D

点击查看答案
第3题
128The project manager must be concerned with building a closely knit team. During the pro

128 The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with:

A. Proposed salary increases if the project is successful

B. Bonuses for early completion date

C. A promise of future assignments

D. Well-defined project objectives

E. Linear responsibility charts

点击查看答案
第4题
Typically, during which phase in a project life cycle are most of the project expenses inc
urred.

A . Concept phase

B . Development of design phase

C . Execution phase.

D . Termination phase.

E . None of the above

点击查看答案
第5题
84Risk management allows the project manager and the project team to: A.eliminate most ris

84 Risk management allows the project manager and the project team to:

A. eliminate most risks during the planning phase of the project

B. identify project risks

C. identify impacts of various risks

D. plan suitable responses

E. B, C and D only

点击查看答案
第6题
97The following reports are normally developed during the project closure phase? A.Communi

97 The following reports are normally developed during the project closure phase?

A. Communications Management Plan and Lessons Learned

B. Records Archive, Closure Report, lessons learned & Formal Acceptance Report

C. Records Archive, Closure Report, & Specifications Document

D. Communications Management Plan and Closure report

E. None of the above

点击查看答案
第7题
Risk management allows the project manager and the project team to:Aeliminate most risks d

Risk management allows the project manager and the project team to:

A eliminate most risks during the planning phase of the project

B identify project risks

C identify impacts of various risks

D plan suitable responses

E B, C and D only

点击查看答案
第8题
The purpose of configuration management is to:A.insure drawings are updatedB.control chang

The purpose of configuration management is to:

A.insure drawings are updated

B.control change throughout the project

C.control change during the production only

D.generate engineering change proposals

E.inform. the project manager of changes

点击查看答案
第9题
21The "buy or make" decision is usually made during the: A.acquisition cycle B.contract ev

21 The "buy or make" decision is usually made during the:

A. acquisition cycle

B. contract evaluation cycle

C. requirements cycle

D. pre-award cycle

E. at any time that is convenient for the project manager

点击查看答案
第10题
Total Project Risk:Ashould not be calculated for small projectsBis the probability of each

Total Project Risk:

A should not be calculated for small projects

B is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

D A and B

E A and C

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改