首页 > 职业资格考试> 项目管理师
题目内容 (请给出正确答案)
[主观题]

Risk can be divided into two basic types; business risk and pure (or insurable risk). Of t

Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?

A liability loss

B direct property loss

C profit loss

D personnel-related loss

E B and C

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“Risk can be divided into two b…”相关的问题
第1题
84Risk can be divided into two basic types; business risk and pure (or insurable risk). Of

84 Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?

A. liability loss

B. direct property loss

C. profit loss

D. personnel-related loss

E. B and C

点击查看答案
第2题
Risk event probability is defined as:Athe total number of possible events divided into the

Risk event probability is defined as:

A the total number of possible events divided into the expectations or frequency of the risk event

B the number of times the risk event may occur

C the fraction of the total project tasks which may be affected by the risk event

D the total number of possible events divided into the consequences of the risk event.

E A and B

点击查看答案
第3题
144Risk event probability is defined as: A.the total number of possible events divided int

144 Risk event probability is defined as:

A. the total number of possible events divided into the expectations or frequency of the risk event

B. the number of times the risk event may occur

C. the fraction of the total project tasks which may be affected by the risk event

D. the total number of possible events divided into the consequences of the risk event.

E. A and B

点击查看答案
第4题
听力原文:M: Can you tell me something about a balance sheet?W: Yes. It is divided into thr

听力原文:M: Can you tell me something about a balance sheet?

W: Yes. It is divided into three sections: assets, liabilities, and owner's equity and it is used to summarize a company's financial position on a given date.

Q: Which of the following is not a section of a balance sheet?

(15)

A.Profit and Joss

B.Owner's equity.

C.Liabilities

D.Assets.

点击查看答案
第5题
Total project risk can be defined as:Athe sum of the probabilities of project risks events

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.

点击查看答案
第6题
(c) Risk committee members can be either executive or non-executive.Required:(i) Distingui

(c) Risk committee members can be either executive or non-executive.

Required:

(i) Distinguish between executive and non-executive directors. (2 marks)

点击查看答案
第7题
Sensitivity analysis can be used in risk analysis to:ASubstitute for uncertainty analysis

Sensitivity analysis can be used in risk analysis to:

A Substitute for uncertainty analysis in risk quantification

B estimate the level of risk aversion adopted by management

C estimate the effect of change of one project variable on the overall project

D A and B

E All of the above.

点击查看答案
第8题
108Project Risk Management is based on which of the following premises: A.the future is un

108 Project Risk Management is based on which of the following premises:

A. the future is unknown.

B. unknowns can result in risks or opportunities.

C. we cannot control risk events.

D. project risk impact can be measured and controlled

E. All of the above

点击查看答案
第9题
听力原文:Seeking to maximize profits by assuming inappropriately large financial risk can
cause investors to lose sleep.

(2)

A.Assuming inappropriately large financial risk can cause investors to lose sleep.

B.Financial risk will not cause investors to lose sleep.

C.Seeking to maximize profits appropriately can cause investors to lose sleep.

D.No matter how much they earn, the investors will lose sleep.

点击查看答案
第10题
Project Risk Management is based on which of the following premises:Athe future is unknown

Project Risk Management is based on which of the following premises:

A the future is unknown.

B unknowns can result in risks or opportunities.

C we cannot control risk events.

D project risk impact can be measured and controlled

E All of the above.

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改